The following is a listing of the regulatory permits and other notable requirements for common activities related to mineral projects. Selecting an activity will bring you to a page that lists the relevant legislation and include links to the relevant statute, regulations and application guides and forms. Please note that some activities may be governed by more than one regulatory requirement.
Visit the Regulation Registry to view regulatory proposals as well as recently approved regulations.
Find your activity in alphabetical order.
Listing: E-L
E
Requirement/ Permit:
Applies To:
- discharges greater than 50 cubic metres per day captured by MISA regulation
Requirement/ Permit:
Applies To:
- federal effluent limits, monitoring and reporting requirements for metal mines
Requirement/ Permit:
- all private sector employment under provincial jurisdiction
Requirement/ Permit:
- Applies when various federal authorizations required or other federal decision required
Requirement/ Permit:
- If project designated under Environmental Assessment Act
Requirement/ Permit:
- If project designated under Environmental Assessment Act
Requirement/ Permit:
- Applies to designated government decision making processes
Requirement/ Permit:
Exploration in designated areas (e.g. Temagami)
Requirement/ Permit:
This activity considered Advanced Exploration
Requirement/ Permit:
Activities within 45 metres of the highway may be controlled for safety considerations
Requirement/ Permit:
required for the transport various types of explosives
Requirement/ Permit:
For the purchase of blasting explosives for personal use when the quantity is below the licensing threshold of 75 kg or storage does not exceed 90 days
Requirement/ Permit:
Licence required for the constructing explosives factory.
Requirement/ Permit:
Licence required constructing or maintaining an explosives magazine
Requirement/ Permit:
Registration of project required prior to purchase of explosives
Requirement/ Permit:
Certification of rough diamonds required for export and import
F
Requirement/ Permit:
Any work resulting in harmful alteration or destruction of fisheries habitat
Requirement/ Permit:
Fish, Collection and possession of fish or other wild life for scientific purposes
Requirement/ Permit:
Authorization required from DFO to destroy fish during any part of a project
Requirement/ Permit:
fuel storing and handling facilities
G
Requirement/ Permit:
fuel storing and handling facilities
H
Requirement/ Permit:
construction / renovating close to or adjacent a provincial highway
Requirement/ Permit:
Activities within 45 metres of the highway may be controlled for safety considerations
Requirement/ Permit:
- Provincial highway
Requirement/ Permit:
- Entrances permit requirements for safe access to highway
Requirement/ Permit:
- Requirement for consent to permit surface mining within 45 m of limits of the highway.
Requirement/ Permit:
- Commercial signs within 400 m of a provincial highway
I
Requirement/ Permit:
- Applies to surrendered mines and minerals underlying lands in a reserve in Ontario
Requirement/ Permit:
Indian reserve
Requirement/ Permit:
Indian reserves
Requirement/ Permit:
construction on Indian reserves
L
Requirement/ Permit:
Authorization through a Land Use Permit to use or occupy Crown land Authorization through Licence of Occupation to use or occupy Crown land Disposition of Crown land and resources
Requirement/ Permit:
Authorisation to occupy for mining purposes
Requirement/ Permit:
Acquisition of surface rights only for mining purposes
Requirement/ Permit:
Applies To:
Voluntary surrender of mining Lands subject to agreement concerning closure liabilities