O. Reg. 563/17: BUILDING CODE

filed December 19, 2017 under Building Code Act, 1992, S.O. 1992, c. 23

Skip to content

 

ontario regulation 563/17

made under the

Building Code Act, 1992

Made: December 13, 2017
Filed: December 19, 2017
Published on e-Laws: January 30, 2018
Printed in The Ontario Gazette: January 6, 2018

Amending O. Reg. 332/12

(BUILDING CODE)

1. (1) Sentence 3.1.21.1.(1) of Division B of Ontario Regulation 332/12 is amended by striking out “Sentence (3)” and substituting “Sentences (2.1) and (3)”.

(2) Article 3.1.21.1. of Division B of the Regulation is amended by adding the following Sentence:

(2.1) Parking spaces located in a building need not comply with Sentence (1) where,

(a) before January 1, 2018,

(i) an agreement was entered into between the owner of the land on which the building is to be constructed and a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, that sets out the conditions for the connection of the building to a distribution system, as defined in subsection 2 (1) of that Act, or

(ii) a plan for the land on which the building is to be constructed respecting the siting and sizing of lines, transformers or other equipment used for conveying electricity was approved by a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, and

(b) an application for a permit to construct the building was made before January 1, 2020.

(3) Sentence 3.1.21.1.(3) of Division B of the Regulation is amended by striking out “Sentence (6)” in the portion before Clause (a) and substituting “Sentences (6) and (7)”.

(4) Article 3.1.21.1. of Division B of the Regulation is amended by adding the following Sentence:

(7) A house need not comply with Sentence (3) where,

(a) before January 1, 2018,

(i) an agreement was entered into between the owner of the land on which the house is to be constructed and a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, that sets out the conditions for the connection of the house to a distribution system, as defined in subsection 2 (1) of that Act, or

(ii) a plan for the land on which the house is to be constructed respecting the siting and sizing of lines, transformers or other equipment used for conveying electricity was approved by a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, and

(b) an application for a permit to construct the house was made before January 1, 2020.

2. (1) Sentence 9.34.4.1.(1) of Division B of the Regulation is amended by striking out “Sentence (3)” and substituting “Sentences (2.1) and (3)”.

(2) Article 9.34.4.1. of Division B of the Regulation is amended by adding the following Sentence:

(2.1) Parking spaces located in a building need not comply with Sentence (1) where,

(a) before January 1, 2018,

(i) an agreement was entered into between the owner of the land on which the building is to be constructed and a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, that sets out the conditions for the connection of the building to a distribution system, as defined in subsection 2 (1) of that Act, or

(ii) a plan for the land on which the building is to be constructed respecting the siting and sizing of lines, transformers or other equipment used for conveying electricity was approved by a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, and

(b) an application for a permit to construct the building was made before January 1, 2020.

(3) Sentence 9.34.4.1.(3) of Division B of the Regulation is amended by striking out “Sentence (6)” in the portion before Clause (a) and substituting “Sentences (6) and (7)”.

(4) Article 9.34.4.1. of Division B of the Regulation is amended by adding the following Sentence:

(7)  A house need not comply with Sentence (3) where,

(a) before January 1, 2018,

(i) an agreement was entered into between the owner of the land on which the house is to be constructed and a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, that sets out the conditions for the connection of the house to a distribution system, as defined in subsection 2 (1) of that Act, or

(ii) a plan for the land on which the house is to be constructed respecting the siting and sizing of lines, transformers or other equipment used for conveying electricity was approved by a distributor, as defined in subsection 2 (1) of the Electricity Act, 1998, and

(b) an application for a permit to construct the house was made before January 1, 2020.

Commencement

3. This Regulation comes into force on the later of January 1, 2018 and the day it is filed.

 

CORRECTION

An incorrect version of this Regulation was published on December 19, 2017.  The correct version was published on January 30, 2018.  This correction notice was posted on January 30, 2018.