Notice of cessation of use for transmission system, etc.
0.1 (1) A notice required by subsection 114.10 (2) of the Act must contain a registrable description of the corridor land to which the notice relates. O. Reg. 332/03, s. 1.
(2) The notice required by subsection 114.10 (2) of the Act may be given to the Chair of Management Board by delivering it to a lawyer employed in the Legal Services Branch of Management Board Secretariat. O. Reg. 332/03, s. 1.
Transfer of ownership by Crown to person with statutory right
1. (1) The Environmental Assessment Act does not apply with respect to a transfer of corridor land under subsection 114.13 (1) of the Act that is made on or before March 31, 2004. O. Reg. 114/03, s. 1.