R.R.O. 1990, Reg. 167: FILL, CONSTRUCTION AND ALTERATION TO WATERWAYS - ST. CLAIR REGION
under Conservation Authorities Act, R.S.O. 1990, c. C.27
Skip to contentrevoked or spent May 4, 2006 | |
December 31, 1990 – May 3, 2006 |
Conservation Authorities Act
Loi sur les offices de protection de la nature
R.R.O. 1990, REGULATION 167
No Amendments
FILL, CONSTRUCTION AND ALTERATION TO WATERWAYS — ST. CLAIR REGION
Historical version for the period December 31, 1990 to May 3, 2006.
This Regulation is made in English only.
1. In this Regulation,
“Authority” means the St. Clair Region Conservation Authority;
“building or structure” means a building or structure of any kind;
“drainage area” means, for a point, the area which contributes runoff to that point;
“fill” means earth, sand, gravel, rubble, rubbish, garbage or any other material whether similar to or different from any of the aforementioned materials, whether originating on the site or elsewhere, used or capable of being used to raise, lower or in any way affect the contours of the ground;
“fill line” means any line designated as such on the maps referred to in the Schedules;
“regional storm” means a storm producing in a forty-eight hour period in a drainage area of,
(a) ten square miles or less, a rainfall that has the distribution set out in Table 1, or
(b) more than ten square miles, a rainfall such that the number of inches of rain referred to in each case in Table 1 shall be modified by the percentage amount shown in Column 2 of Table 1 opposite the size of the drainage area set out opposite thereto in Column 1 of Table 2:
TABLE 1
2.90 inches of rain in the first 36 hours |
0.25 inches of rain in the 37th hour |
0.17 inches of rain in the 38th hour |
0.25 inches of rain in the 39th hour |
0.50 inches of rain in the 40th hour |
0.66 inches of rain in the 41st hour |
0.50 inches of rain in the 42nd hour |
0.91 inches of rain in the 43rd hour |
0.50 inches of rain in the 44th hour |
0.50 inches of rain in the 45th hour |
2.08 inches of rain in the 46th hour |
1.49 inches of rain in the 47th hour |
0.50 inches of rain in the 48th hour |
TABLE 2
Column 1 |
Column 2 |
Drainage Area (square miles) |
Percentage |
11 to 17 both inclusive |
99.2 |
18 to 25 both inclusive |
98.2 |
26 to 35 both inclusive |
97.1 |
36 to 45 both inclusive |
96.3 |
46 to 55 both inclusive |
95.4 |
56 to 65 both inclusive |
94.8 |
66 to 75 both inclusive |
94.2 |
76 to 85 both inclusive |
93.5 |
86 to 95 both inclusive |
92.7 |
96 to 105 both inclusive |
92.0 |
106 to 175 both inclusive |
89.4 |
176 to 225 both inclusive |
86.7 |
226 to 275 both inclusive |
84.0 |
276 to 325 both inclusive |
82.4 |
326 to 375 both inclusive |
80.8 |
376 to 450 both inclusive |
79.3 |
451 to 550 both inclusive |
76.6 |
551 to 650 both inclusive |
74.4 |
651 to 750 both inclusive |
73.3 |
751 to 850 both inclusive |
71.7 |
851 to 950 both inclusive |
70.2 |
951 to 1050 both inclusive |
69.0 |
1051 to 1750 both inclusive |
64.4 |
1751 to 2250 both inclusive |
61.4 |
2251 to 2750 both inclusive |
58.9 |
2751 to 3000 both inclusive |
57.4 |
“river”, “lake”, “creek”, “stream” or “watercourse” means any river, lake, creek, stream or watercourse under the jurisdiction of the Authority. R.R.O. 1990, Reg. 167, s. 1.
2. The areas described in the Schedules are areas in which, in the opinion of the Authority, the control of flooding or pollution or the conservation of land may be affected by the placing or dumping of fill. R.R.O. 1990, Reg. 167, s. 2.
3. Subject to section 4, no person shall,
(a) construct any building or structure or permit any building or structure to be constructed in or on a pond or swamp or in any area susceptible to flooding during a regional storm;
(b) place or dump fill or permit fill to be placed or dumped in the areas described in the Schedules whether such fill is already located in or upon such area, or brought to or on such area from some other place or places; or
(c) straighten, change, divert or interfere in any way with the existing channel of a river, creek, stream or watercourse. R.R.O. 1990, Reg. 167, s. 3.
4. Subject to the Ontario Water Resources Act or to any private interest, the Authority may permit in writing the construction of any building or structure or the placing or dumping of fill or the straightening, changing, diverting or interfering with the existing channel of a river, creek, stream or watercourse to which section 3 applies if, in the opinion of the Authority, the site of the building or structure or the placing or dumping and the method of construction or placing or dumping or the straightening, changing, diverting or interfering with the existing channel will not affect the control of flooding or pollution or the conservation of the land. R.R.O. 1990, Reg. 167, s. 4.
5. No person shall commence to construct any building or structure or dump or place fill or straighten, change, divert or interfere with the existing channel of a river, creek, stream or watercourse in any area to which section 3 applies before permission to do so has been obtained under section 4. R.R.O. 1990, Reg. 167, s. 5.
6. (1) A signed application for permission to construct a building or structure shall be filed with the Authority and shall include,
(a) four copies of a plan of the property showing the proposed location of the building or structure, its elevation and the proposed final grade plan;
(b) four copies of a complete description of the type of building or structure to be constructed, including drainage details;
(c) four copies of a statement of the dates between which the construction will be carried out; and
(d) four copies of a statement of the proposed use of the building or structure following completion of the construction.
(2) A signed application for permission to place or dump fill shall be filed with the Authority and shall include,
(a) four copies of a plan of the property on which the fill is to be placed, showing the proposed location of filling, the depth to which it is proposed to fill and the proposed final grade of the land when filling is completed;
(b) four copies of a complete description of the type of fill proposed to be placed or dumped;
(c) four copies of a statement of the dates between which the placing or dumping will be carried out; and
(d) four copies of a statement of the proposed use of the land following completion of placing or dumping.
(3) A signed application for permission to straighten, change, divert or interfere in any way with the existing channel of a river, creek, stream or watercourse, shall be filed with the Authority and shall include,
(a) four copies of a plan on which shall be shown in plan view and cross section the details of such straightening, change, diversion or interference;
(b) four copies of a description of the protective measures to be undertaken;
(c) four copies of a statement of the dates between which the straightening, changing, diverting or interfering will be carried out; and
(d) four copies of a statement of the purpose of the proposed work. R.R.O. 1990, Reg. 167, s. 6.
7. The Authority may, at any time, withdraw any permission given under this Regulation, if, in the opinion of the Authority, the conditions of the permit are not complied with. R.R.O. 1990, Reg. 167, s. 7.
8. Members of the staff of the Authority are appointed officers to enforce this Regulation. R.R.O. 1990, Reg. 167, s. 8.
SCHEDULE 1
Being composed of lands in the counties of Kent, Lambton and Middlesex that extend the distance from the streams, lake or watercourses shown by the shaded areas on the maps filed in the office of the Registrar of Regulations at Toronto as Nos. 1257 to 1260, both inclusive, and described as follows:
1. That part of Running Creek and that part of the Sydenham River and their tributaries from the point of their entry into River Chenal Ecarte in the townships of Chatham and Dover, respectively, in the County of Kent, to the south and west boundaries of the Town of Wallaceburg in the County of Kent.
2. That part of the North branch of the Sydenham River and its tributaries, including Otter Creek, from the north boundary of the Town of Wallaceburg to the junction of Bear and Black Creeks in the Township of Sombra in the County of Lambton.
3. The whole of Black Creek and its tributaries from its junction with Bear Creek in the Township of Sombra in the County of Lambton.
4. That part of Bear Creek and its tributaries from its junction with Black Creek in the Township of Sombra in the County of Lambton, to the south boundary of the Town of Petrolia.
5. That part of Bear Creek and its tributaries from the north boundary of the Town of Petrolia to its source in the Township of Warwick in the County of Lambton.
6. That part of the east branch of the Sydenham River and its tributaries from the easterly limit of County Road No. 15, the division between Concession 7 and Concession 8 in the Township of Camden, in the County of Kent, to the southwest boundary of Schedule V, more specifically defined as the westerly limit of Lot 20, Concession 1 in the Township of Metcalfe and the west boundary of the Town of Strathroy, both in the County of Middlesex.
7. That part of the east branch of the Sydenham River and its tributaries, including those flowing into the Town of Strathroy, from the north, northeast and southeast boundaries of the Town of Strathroy to its source in the Township of London in the County of Middlesex.
R.R.O. 1990, Reg. 167, Sched. 1.
SCHEDULE 2
Within the limits of the Town of Wallaceburg and being that area of land below the high-water mark bounded generally by the 580 ft. contour line as shown shaded on the maps filed in the office of the Registrar of Regulations at Toronto as Nos. 1260 to 1264, both inclusive.
Saving and excepting thereout and therefrom:
1. That built up area bounded on the east by the limits of the Town of Wallaceburg and described as follows:
Beginning at a point on the Chesapeake and Ohio Railway Line at the line between the east boundary of the Town of Wallaceburg and the west boundary of Lot 14, Concession I, in the Township of Chatham, in the County of Kent; thence westerly along the southerly limit of the Chesapeake and Ohio Railway Line across Gillard Street to the Chesapeake and Ohio Railway spur; thence westerly along the southerly limit of said spur to the 580 ft. contour running parallel to and just south of Wallace Street; thence easterly along this 580 ft. contour, bordering the south bank of the Sydenham River to the easterly limits of the Town of Wallaceburg.
2. That area of land generally below the 580 ft. contour lines, shown shaded and described as follows:
Beginning at the point where the 580 ft. contour bordering Running Creek meets the easterly limit of Forhan Street; thence southerly along the easterly limit to the southerly limit of Haig Street; thence westerly along the southerly limit to the easterly limit of First Street; thence southerly along the easterly limit to the southerly limit of Dufferin Ave.; thence westerly along the southerly limit to the westerly limit of the Chesapeake and Ohio Railway Line; thence southerly along that westerly limit to the 580 ft. contour which it meets at Forhan Street; thence southerly along the 580 ft. contour until it reaches a point near the Sydenham River; thence northerly along the 580 ft. contour on the east bank of the Sydenham River, and latterly, on the east bank of the north branch of the Sydenham River, to a point near Running Creek; thence westerly along the 580 ft. contour on the south bank of Running Creek to the place of beginning.
R.R.O. 1990, Reg. 167, Sched. 2.
SCHEDULE 3
That part of the east branch of the Sydenham River below the marked elevations extending easterly from the east boundary of the Town of Wallaceburg in the County of Kent to the westerly limit of County Kent Road No. 15, the division between Concession VII and Concession VIII in the Township of Camden in the County of Kent, as shown on maps filed in the office of the Registrar of Regulations at Toronto as Nos. 1265 to 1274, both inclusive.
R.R.O. 1990, Reg. 167, Sched. 3.
SCHEDULE 4
That part of the watershed of Bear Creek and its tributaries below the 650 ft. contour interval within the limits of the Town of Petrolia, in the County of Lambton, as shown on the maps filed in the office of the Registrar of Regulations at Toronto as Nos. 1275 and 1276.
R.R.O. 1990, Reg. 167, Sched. 4.
SCHEDULE 5
1. That part of the watershed of the east branch of the Sydenham River and its tributaries within the limits of the Town of Strathroy; in the County of Middlesex, as shown on the maps filed in the office of the Registrar of Regulations at Toronto as Nos. 1277 and 1278.
2. That part of the watershed of the unnamed tributary of the east branch of the Sydenham River within Lot 20, Concession V, in the Township of Adelaide, in the County of Middlesex, and Lot 9, Concession X, and the northwest one-quarter of Lot 8, Concession X, in the Township of Caradoc, in the County of Middlesex, as shown on the map filed in the office of the Registrar of Regulations at Toronto as No. 1260.
R.R.O. 1990, Reg. 167, Sched. 5.