O. Reg. 307/17: EFFLUENT MONITORING AND EFFLUENT LIMITS - METAL CASTING SECTOR, Filed July 28, 2017 under Environmental Protection Act, R.S.O. 1990, c. E.19

 

ontario regulation 307/17

made under the

Environmental Protection Act

Made: July 26, 2017
Filed: July 28, 2017
Published on e-Laws: July 31, 2017
Printed in The Ontario Gazette: August 12, 2017

Amending O. Reg. 562/94

(EFFLUENT MONITORING AND EFFLUENT LIMITS - METAL CASTING SECTOR)

1. (1) The definition of “assessment parameter” in subsection 1 (1) of Ontario Regulation 562/94 is revoked and the following substituted:

“assessment parameter”, in relation to a plant, means a parameter that is listed in the Table for the plant in Schedule 3;

(2) The definition of “limited parameter” in subsection 1 (1) of the Regulation is amended by adding “the Table for the plant in” before “Schedule 2”.

2. Subsections 15 (1) and (2) of the Regulation are amended by adding “the Table for the plant in” before “Schedule 2” wherever it appears.

3. Subsection 18 (1) of the Regulation is amended by adding “the table in” before “Schedule 2”.

4. Subsection 19 (1) of the Regulation is amended by adding “the table in” before “Schedule 2”.

5. Subsection 21 (1) of the Regulation is amended by adding “the table in” before “Schedule 2”.

6. Subsection 26 (1) of the Regulation is amended by adding “the table in” before “Schedule 3”.

7. Schedules 2 and 3 to the Regulation are revoked and the following substituted:

Schedule 2
Process Effluent Limits and Monitoring Frequency

TABLE 1
Ford Motor Company of Canada, Limited Windsor Casting Plant Windsor

Item

Analytical Test Group

Column 1

Parameter

Column 2

Monitoring Frequency

Column 3

Daily Plant Loading Limit

in kilograms per day

Column 4

Monthly Average Plant Loading Limit

in kilograms per day

1.

2

Total Cyanide

Weekly

25.0

Not applicable

2.

5a

Dissolved Organic Carbon (DOC)

Daily

884

317

3.

8

Total Suspended Solids (TSS)

Daily

3220

847

4.

9

Aluminum

Weekly

530

107

5.

9

Zinc

Weekly

137

29.7

6.

14

Phenolics (4AAP)

Daily

34.4

7.34

TABLE 2
HALEY INDUSTRIES LTD., HALEY

Item

Analytical Test Group

Column 1

Parameter

Column 2

Monitoring Frequency

Column 3

Daily Plant Loading Limit

in kilograms per day

Column 4

Monthly Average Plant Loading Limit

in kilograms per day

1.

1a

Biochemical Oxygen Demand

Weekly

8.85

3.60

2.

2

Total Cyanide

Weekly

1.00

0.393

3.

4a

Ammonia plus Ammonium

Weekly

13.1

7.22

4.

6

Total Phosphorus

Weekly

0.844

0.309

5.

8

Total Suspended Solids (TSS)

Daily

17.8

3.60

6.

9

Aluminum

Weekly

1.69

0.360

7.

9

Chromium

Weekly

0.650

0.144

8.

9

Copper

Weekly

0.534

0.144

9.

9

Silver

Weekly

0.286

0.106

10.

9

Zinc

Weekly

0.749

0.144

11.

14

Phenolics (4AAP)

Daily

0.0433

0.00703

Schedule 3
Cooling Water Assessment Monitoring Requirements

TABLE 1
Canada Alloy Casting Ltd., Kitchener

Item

Analytical Test Group

Column 1

Parameter

Column 2

Monitoring Frequency

1.

5a

Dissolved Organic Carbon (DOC)

Weekly

2.

8

Total Suspended Solids (TSS)

Weekly

TABLE 2
CHRYSLER, ETOBICOKE CASTING PLANT, TORONTO

Item

Analytical Test Group

Column 1

Parameter

Column 2

Monitoring Frequency

1.

5a

Dissolved Organic Carbon (DOC)

Weekly

2.

8

Total Suspended Solids (TSS)

Weekly

3.

30

Fluoride

Weekly

TABLE 3
Kubota Metal Corporation, Fahramet Division, Orillia

Item

Analytical Test Group

Column 1

Parameter

Column 2

Monitoring Frequency

1.

5a

Dissolved Organic Carbon (DOC)

Weekly

2.

8

Total Suspended Solids (TSS)

Weekly

3.

14

Phenolics (4AAP)

Weekly

TABLE 4
Western Foundry Company Limited, Wingham

Item

Analytical Test Group

Column 1

Parameter

Column 2

Monitoring Frequency

1.

5a

Dissolved Organic Carbon (DOC)

Weekly

2.

8

Total Suspended Solids (TSS)

Weekly

3.

14

Phenolics (4AAP)

Weekly

4.

30

Fluoride

Weekly

Commencement

8. This Regulation comes into force on the day it is filed.