Environmental Assessment Act

Section 17.15

Notice of Approval to proceed with a Part II.3 project

RE: The Waasigan Transmission Line Project Amended Environmental Assessment

Proponent: Hydro One Networks Inc. (Hydro One)

EA File No.: 03-03-03

EA Reference No.: 16055

Part II.3 of the Environmental Assessment Act (the Act) establishes the requirements, authority, and process for preparing, submitting, and deciding an application for approval to proceed with a Part II.3 Project under the Act. An application consists of a proposed terms of reference and environmental assessment. In respect of the Project, the Proposed Terms of Reference, Waasigan Transmission Line Environmental Assessment was approved by the minister on February 18, 2022. The Proponent submitted its Environmental Assessment on November 17, 2023, for a decision on the application.

A nine-week comment period followed the submission of the Environmental Assessment to the ministry, during which time any person could submit comments about the Environmental Assessment and the Project. On May 1, 2024, Hydro One submitted an amended Environmental Assessment to the ministry.

The ministry review of the amended Environmental Assessment was completed on June 21, 2024, and notice was provided in accordance with the Act. The ministry review concluded that the amended Environmental Assessment was prepared in accordance with the approved amended Terms of Reference and the Act and contained sufficient information to assess the potential environmental effects of the Project. There were no outstanding issues from the Environmental Assessment process. The public, government agencies and Indigenous communities had an opportunity to comment on the Environmental Assessment, the Project, and the ministry review during the five-week comment period.

The Proponent and ministry provided identified Indigenous communities with opportunities for consultation with respect to the terms of reference, the Environmental Assessment and the ministry review.

All comments submitted during the statutory comment periods have been considered. Three requests for a hearing by the Ontario Land Tribunal were submitted. I do not find a hearing necessary in this case, and am not aware of any outstanding issues with respect to the application which suggest that a hearing should otherwise be required.

Having considered the purpose of the Environmental Assessment Act, the approved amended Terms of Reference, the amended Environmental Assessment, the ministry review of the amended Environmental Assessment and submissions received, I hereby give approval to proceed with the Project, subject to the conditions set out below.

Reasons

My reasons for my decision are:

  1. The Proponent has complied with the requirements of the Environmental Assessment Act.
  2. The amended Environmental Assessment has been prepared in accordance with the approved amended Terms of Reference.
  3. Taking into consideration the Proponent’s amended Environmental Assessment and the ministry review, the Proponent’s conclusion that, on balance, the advantages of this Project outweigh its disadvantages appears to be valid.
  4. The Proponent has demonstrated that the environmental effects of the Project can be appropriately avoided, managed, mitigated.
  5. Taken together, the Proponent’s amended Environmental Assessment, the Ministry Review and the conditions of approval, the approval of the Project would be consistent with the purpose of the Environmental Assessment Act.
  6. There are no outstanding concerns raised by government agency, public or Indigenous communities that cannot be addressed through commitments in the amended Environmental Assessment, through the conditions set out below or through future approvals that will be required.

Conditions of approval

The approval is subject to the following conditions:

Act
means the Environmental Assessment Act
Construction
means the physical construction activities, including site preparation works, but does not include the tendering of contracts.
Date of Approval
means the date on which the Order in Council pertaining to the approval of the Project was signed by the Lieutenant Governor-in-Council.
District Manager
means the Manager of the Ministry’s Thunder Bay and Kenora District Offices.
Director
means the Director of the Environmental Assessment Branch.
Environmental Assessment
means the documents titled Amended Environmental Assessment Report for the Waasigan Transmission Line Project.
Environmental Compliance Approval
means an approval issued under Part II.1 of the Environmental Protection Act, R.S.O. 1990, c.E.19, as amended.
Indigenous Communities
means the following communities which the Proponent consulted for the proposed Project: Eagle Lake First Nation, Fort William First Nation, Gakijiwanong Anishinaabe Nation, Lac Seul First Nation, Ojibway Nation of Saugeen, Seine River First Nation, Nigigoonsiminikaaning First Nation, Wabigoon Lake Ojibway Nation, Lac des Mille Lacs First Nation, Mitaanjigamiing First Nation, Couchiching First Nation, Northwestern Ontario Métis Community (NWOMC) and Region 2, and Red Sky Métis Independent Nation.
Ministry
means the Ministry of the Environment, Conservation and Parks.
“Program
means the environmental assessment compliance monitoring program.
Project
means the new overhead Alternating Current 230 kilovolt (kV) transmission lines and associated components (e.g., tower structures) modifications to existing infrastructure at the Lakehead Transformer Station (TS), Mackenzie TS and Dryden TS, and separation of the existing 230 kV transmission lines (circuits F25A and D26A) out of the Mackenzie TS in Atikokan; development of temporary supportive infrastructure associated with construction and, development of associated permanent infrastructure as set out in the amended Environmental Assessment.
“Proponent”
means Hydro One Networks Inc. (Hydro One).
“Site”
means the 360-kilometre transmission line corridor between the Municipality of Shuniah and the City of Dryden.

Dated the 9th day of September 2024 at Toronto.

[Original Signed by]
Minister of the Environment, Conservation and Parks
777 Bay Street, 5th Floor
Toronto, Ontario M7A 2J3

Approved by O.C. No.
Date O.C. Approved


Order in Council 1279/2024