Summary

The Ministry of Infrastructure (MOI) is building Ontario by leading the overall development of infrastructure policy and planning to modernize the Province’s infrastructure and strengthen Ontario's communities and economy.

The ministry guides the Province's infrastructure plan by collecting, standardizing, and analyzing data to support evidence-based infrastructure planning and decision-making. As part of the effort to guide Ontario’s infrastructure plan and to ensure the government’s plan for long-term prosperity, MOI is responsible for developing, delivering and negotiating infrastructure programs, including federal-provincial municipal programs as well as implementing policies that support community infrastructure. The ministry oversees the Transit-Oriented Communities (TOC) Program to support the building of vibrant, mixed-use communities near transit and leads the redevelopment of Ontario Place. MOI also leads the government’s commitment to connect communities to high-speed internet access. The ministry also manages the Unsolicited Proposals framework. In addition, the ministry is responsible for managing the government's General Real Estate Portfolio through policy work and program delivery.

As part of its agency oversight role, the ministry has legislative responsibility for Infrastructure Ontario, Waterfront Toronto, the Ontario Place Corporation and the Ontario Science Centre.

The ministry also provides support for the Queen’s Park Restoration Project to ensure this historic heritage building where critical government and parliamentary business is conducted is brought to current building standards. It will ensure this landmark that symbolizes and facilitates the province’s democratic process is protected and remains safe for future use.

Ministry Program Summary

VoteProgram

Estimates
2024-25 $

Estimates
2023-24 $

Difference
between
2024-25
and
2023-24 $

Actual
2022-23 $

Operating expense

4001Ministry Administration11,865,3008,846,6003,018,7009,345,408
4003Infrastructure Policy, Planning, and Projects98,941,10087,180,40011,760,70043,110,699
4006Government Real Estate387,259,900334,723,60052,536,300345,979,903
4007Infrastructure Partnership Projects & Agency Oversight49,107,70032,266,00016,841,70029,734,780
 Total operating expense to be voted547,174,000463,016,60084,157,400428,170,790
 Statutory appropriations225,187225,187-78,561
 Ministry total operating expense547,399,187463,241,78784,157,400428,249,351
 Consolidation Adjustment - General Real Estate Portfolio741,034,900532,611,200208,423,700578,570,926
 Consolidation Adjustment - Ontario Infrastructure and Lands Corporation248,957,700153,410,50095,547,200125,920,968
 Consolidation Adjustment - Toronto Waterfront Revitalization Corporation517,4001,270,200(752,800)28,723,873
 Consolidation Adjustment - Transmission Corridor Program(39,669,600)(22,371,200)(17,298,400)(25,553,048)
 Consolidation Adjustment - Ontario Science Centre16,180,30016,499,400(319,100)5,385,605
 Consolidation Adjustment - Ontario Place Corporation-8,078,200(8,078,200)7,815,774
 Total including consolidation & other adjustments1,514,419,8871,152,740,087361,679,8001,149,113,449

Operating assets

4007Infrastructure Partnership Projects & Agency Oversight-171,230,800(171,230,800)-
 Total operating assets to be voted-171,230,800(171,230,800)-
 Ministry Total operating assets-171,230,800(171,230,800)-

Capital expense

4003Infrastructure Policy, Planning, and Projects2,442,213,3001,650,275,100791,938,200962,809,188
4006Government Real Estate268,305,600125,916,100142,389,500173,987,070
4007Infrastructure Partnership Projects & Agency Oversight484,401,800373,535,300110,866,50020,227,200
 Total capital expense to be voted3,194,920,7002,149,726,5001,045,194,2001,157,023,458
 Statutory appropriations1,490,400430,5001,059,900-
 Ministry total capital expense3,196,411,1002,150,157,0001,046,254,1001,157,023,458
 Consolidation Adjustment - General Real Estate Portfolio(28,034,800)198,507,600(226,542,400)129,524,466
 Consolidation Adjustment - Ontario Infrastructure and Lands Corporation5,926,0004,000,0001,926,000(17,920,509)
 Consolidation Adjustment - Toronto Waterfront Revitalization Corporation3,00019,300(16,300)46,090
 Consolidation Adjustment - Ontario Place Corporation-339,000(339,000)248,359
 Consolidation Adjustment - Ontario Science Centre1,812,4002,743,200(930,800)(1,708,749)
 Total including consolidation & other adjustments3,176,117,7002,355,766,100820,351,6001,267,213,115

Capital assets

4003Infrastructure Policy, Planning, and Projects1,0001,000--
4006Government Real Estate175,541,700366,892,100(191,350,400)278,592,210
4007Infrastructure Partnership Projects & Agency Oversight88,086,30055,924,00032,162,300-
 Total capital assets to be voted263,629,000422,817,100(159,188,100)278,592,210
 Ministry total capital assets263,629,000422,817,100(159,188,100)278,592,210
 Ministry total operating and capital including consolidation and other adjustments (not including assets)4,690,537,5873,508,506,1871,182,031,4002,416,326,564

Reconciliation to previously published data

Operating expense

Estimates
2023-24 $

Actual
2022-23 $

Total operating expense previously published footnote 1443,822,98751,745,568
Government Reorganization  

   Transfer of functions from other Ministries

19,418,800376,503,783
Restated Total operating expense463,241,787428,249,351
Capital expense

Estimates
2023-24 $

Actual
2022-23 $

Total capital expense previously published footnote 22,150,157,000962,809,188
Government Reorganization  

   Transfer of functions from other Ministries

-194,214,270
Restated total capital expense2,150,157,0001,157,023,458
Capital assets

Estimates
2023-24 $

Actual
2022-23 $

Total capital assets previously published footnote 3422,817,100-
Government Reorganization  

   Transfer of functions from other Ministries

-278,592,210
Restated total capital assets422,817,100278,592,210

Ministry Administration - Vote 4001

The ministry’s internal Administration Program provides strategic and operational advice and support services to enable the ministry to achieve government objectives and fiscal priorities. The program provides financial, human resources, planning, legal, communication and other corporate services to support the ministry's funding programs and initiatives.

Vote summary

Item numberItem

Estimates
2024-25 $

Estimates
2023-24 $

Difference
between
2024-25
and
2023-24 $

Actual
2022-23 $

Operating expense

1Ministry Administration11,865,3008,846,6003,018,7009,345,408
 Total operating expense to be voted11,865,3008,846,6003,018,7009,345,408
SMinister’s Salary, the Executive Council Act47,84147,841-49,301
SParliamentary Assistant’s Salary, the Executive Council Act16,17316,173-29,260
 Total statutory appropriations64,01464,014-78,561
 Total operating expense11,929,3148,910,6143,018,7009,423,969

Standard account by item and sub-items

Vote-
item
number
Standard account by item and sub-itemsAmount $Amount $
 Operating expense  
4001-1Ministry Administration  
 

Salaries and wages

 8,332,300
 

Employee benefits

 760,700
 

Transportation and communication

 94,400
 

Services

 2,604,900
 

Supplies and equipment

 73,000
 Total operating expense to be voted 11,865,300
 Sub-items:  
 Main office  
 

Salaries and wages

4,122,600 
 

Employee benefits

232,000 
 

Transportation and communication

34,400 
 

Services

30,000 
 

Supplies and equipment

34,4004,453,400
 Corporate Services  
 

Salaries and wages

3,057,000 
 

Employee benefits

380,000 
 

Transportation and communication

13,300 
 

Services

559,800 
 

Supplies and equipment

13,3004,023,400
 Communications Services  
 

Salaries and wages

1,009,900 
 

Employee benefits

131,300 
 

Transportation and communication

19,600 
 

Services

168,900 
 

Supplies and equipment

19,6001,349,300
 Legal Services  
 

Salaries and wages

142,800 
 

Employee benefits

17,400 
 

Transportation and communication

27,100 
 

Services

1,846,200 
 

Supplies and equipment

5,7002,039,200
 Total operating expense to be voted 11,865,300
 Statutory appropriations  
Statutory

Minister’s Salary, the Executive Council Act

 47,841
Statutory

Parliamentary Assistant’s Salary, the Executive Council Act

 16,173
 Total operating expense for Ministry Administration 11,929,314

Infrastructure Policy, Planning, and Projects - Vote 4003

Infrastructure Policy, Planning and Projects leads overall policy across government to modernize the Province's infrastructure and to deliver on its investments. This infrastructure includes, but is not limited to: highways, roads, bridges, transit, hospitals, colleges, schools, courthouses, correctional facilities and other government buildings.

The program is the steward of provincial asset management planning and develops tools and supports to track current infrastructure assets and planned investments across government. Further, the program collects data and develops tools and analysis of infrastructure condition, capacity and modernization needs to help inform decision making on infrastructure investments across sectors. It also promotes provincial asset management best practices, advances infrastructure policy discussions with other ministries and provides the ministry’s central agency support role, working with Treasury Board Secretariat, to inform the prioritization of infrastructure investments across government.

In addition, the program manages the government's relationship with the federal and municipal governments on infrastructure investments, oversees the delivery of municipal infrastructure policy and programs to ensure alignment with broader provincial infrastructure policy, and develops regulations for asset management plans for municipalities to help them plan their infrastructure priorities and provide evidence to support provincial funding decisions. This includes leading the government's commitment to provide access to high speed internet to communities across Ontario by the end of 2025.

Vote summary

Item numberItem

Estimates
2024-25 $

Estimates
2023-24 $

Difference
between
2024-25
and
2023-24 $

Actual
2022-23 $

Operating expense

1Infrastructure Policy, Planning, and Projects98,941,10087,180,40011,760,70043,110,699
 Total operating expense to be voted98,941,10087,180,40011,760,70043,110,699
SBad Debt Expense, the Financial Administration Act1,0001,000--
 Total statutory appropriations1,0001,000--
 Total operating expense98,942,10087,181,40011,760,70043,110,699

Capital expense

2Infrastructure Policy, Planning and Projects2,442,213,3001,650,275,100791,938,200962,809,188
 Total capital expense to be voted2,442,213,3001,650,275,100791,938,200962,809,188
SAmortization, the Financial Administration Act1,0001,000--
 Total statutory appropriations1,0001,000--
 Total capital expense2,442,214,3001,650,276,100791,938,200962,809,188

Capital assets

8Infrastructure Policy, Planning, and Projects1,0001,000--
 Total capital assets to be voted1,0001,000--
 Total capital assets1,0001,000--

Standard account by item and sub-items

Vote-
item
number
Standard account by item and sub-itemsAmount $Amount $Amount $
 Operating expense   
4003-1Infrastructure Policy, Planning, and Projects   
 

Salaries and wages

  15,584,600
 

Employee benefits

  1,960,000
 

Transportation and communication

  175,300
 

Services

  31,193,200
 

Supplies and equipment

  177,300
 

Transfer payments

   
 

Community Infrastructure Interest Incentives

 1,000 
 

Broadband and Cellular Infrastructure - Operating

 48,650,000 
 

Asset Management

 1,199,70049,850,700
 Total operating expense to be voted  98,941,100
 Sub-items:   
 Infrastructure Programs and Projects   
 

Salaries and wages

 13,642,800 
 

Employee benefits

 1,706,800 
 

Transportation and communication

 100,500 
 

Services

 18,598,400 
 

Supplies and equipment

 102,500 
 

Transfer payments

   
 

Community Infrastructure Interest Incentives

1,000  
 

Asset Management

1,198,7001,199,70035,350,700
 Infrastructure Strategy, Policy & Research   
 

Salaries and wages

 1,941,800 
 

Employee benefits

 253,200 
 

Transportation and communication

 74,800 
 

Services

 5,794,800 
 

Supplies and equipment

 74,800 
 

Transfer payments

   
 

Asset Management

 1,0008,140,400
 Broadband Strategy   
 

Services

 6,800,000 
 

Transfer payments

   
 

Broadband and Cellular Infrastructure - Operating

 48,650,00055,450,000
 Total operating expense to be voted  98,941,100
 Statutory appropriations   
 

Other transactions

   
Statutory

Bad Debt Expense, the Financial Administration Act

  1,000
 Total operating expense for Infrastructure Policy, Planning, and Projects  98,942,100
 Capital expense   
4003-2Infrastructure Policy, Planning and Projects   
 

Transfer payments

   
 

Rural and Northern Infrastructure - Federal Contribution

 31,336,900 
 

Community, Culture and Recreation (Provincial Contributions)

 70,817,600 
 

Community, Culture and Recreation (Federal Contributions)

 135,823,900 
 

Green Infrastructure (Provincial Contributions)

 52,357,100 
 

Green Infrastructure (Federal Contributions)

 69,114,100 
 

Rural and Northern Infrastructure - Provincial Contribution

 13,288,800 
 

Broadband and Cellular Infrastructure

 1,298,014,400 
 

Strategic Priorities and Infrastructure Fund

 47,060,000 
 

ICIP - COVID-19 Resilience (Provincial Contribution)

 8,925,700 
 

ICIP - COVID-19 Resilience (Federal Contribution)

 35,080,800 
 

Housing-Enabling Water Systems Fund

 150,000,000 
 

Municipal Housing Infrastructure Program

 125,000,000 
 

Clean Water and Wastewater Fund - Federal Contributions

 950,800 
 

Clean Water and Wastewater Fund - Provincial Contributions

 473,600 
 

Federal - Provincial Infrastructure Programs - Provincial Contributions

 3,334,300 
 

Municipal Infrastructure Investment Initiative

 3,552,000 
 

Municipal Infrastructure

 397,082,3002,442,212,300
 

Other transactions

  1,000
 Total capital expense to be voted  2,442,213,300
 Statutory appropriations   
 

Other transactions

   
Statutory

Amortization, the Financial Administration Act

  1,000
 Total capital expense for Infrastructure Policy, Planning, and Projects  2,442,214,300
 Capital assets   
4003-8Infrastructure Policy, Planning, and Projects   
 

Machinery and equipment - asset costs

  1,000
 Total capital assets to be voted  1,000
 Total capital assets for Infrastructure Policy, Planning, and Projects  1,000

Government Real Estate - Vote 4006

The Government Real Estate Program is responsible for managing the government's General Real Estate Portfolio through policy work and program delivery.

The program oversees real estate management activities of the Ontario Infrastructure and Lands Corporation (Infrastructure Ontario) to implement real estate strategies, portfolio planning, multi-year acquisition and disposal of surplus properties, and capital planning. The ministry's Contaminated Sites Plan, the Forfeited Corporate Property Program and the Transmission Corridor Program are managed by this program.

The program is also responsible for optimizing the Province's office real estate and driving workplace transformation to reduce costs and ensure the greatest value from public sector real estate assets of government and agencies. This is achieved through better management of realty assets and service delivery, by reducing costly third party leased office space and modernizing office space where the Ontario Public Service works to deliver the best outcomes and services for Ontarians. Major realty projects are delivered through this program, including the Macdonald Block reconstruction project.

The program also includes the oversight of the Queens Park Restoration Project

Vote summary

Item numberItem

Estimates
2024-25 $

Estimates
2023-24 $

Difference
between
2024-25
and
2023-24 $

Actual
2022-23 $

Operating expense

1Government Real Estate380,168,800333,765,90046,402,900345,282,588
5Legislative Building Restoration7,091,100957,7006,133,400697,315
 Total operating expense to be voted387,259,900334,723,60052,536,300345,979,903
SBad Debt Expense, the Financial Administration Act144,000144,000--
SParliamentary Assistant's Salary, the Executive Council Act16,17316,173--
 Total statutory appropriations160,173160,173--
 Total operating expense387,420,073334,883,77352,536,300345,979,903

Capital expense

2Government Real Estate268,304,600125,723,600142,581,000173,987,070
3Government Real Estate – Capital expense Related to Capital assets1,000192,500(191,500)-
 Total capital expense to be voted268,305,600125,916,100142,389,500173,987,070
SAmortization, the Financial Administration Act1,289,400429,500859,900-
 Total statutory appropriations1,289,400429,500859,900-
 Total capital expense269,595,000126,345,600143,249,400173,987,070

Capital assets

4Government Real Estate175,541,700366,892,100(191,350,400)278,592,210
 Total capital assets to be voted175,541,700366,892,100(191,350,400)278,592,210
 Total capital assets175,541,700366,892,100(191,350,400)278,592,210

Standard account by item and sub-items

Vote-
item
number
Standard account by item and sub-itemsAmount $Amount $
 Operating expense  
4006-1Government Real Estate  
 

Salaries and wages

 12,204,700
 

Employee benefits

 1,418,300
 

Transportation and communication

 130,800
 

Services

 383,373,600
 

Supplies and equipment

 147,600
 

Transfer payments

  
 

Realty Transactions - Operating

 1,000
 

Other transactions

 12,269,700
 Subtotal 409,545,700
 Less: recoveries 29,376,900
 Total operating expense to be voted 380,168,800
 Sub-items:  
 Realty  
 

Salaries and wages

5,554,500 
 

Employee benefits

610,900 
 

Transportation and communication

83,300 
 

Services

283,384,600 
 

Supplies and equipment

89,300 
 

Transfer payments

  
 

Realty Transactions - Operating

1,000 
 

Other transactions

12,269,700301,993,300
 Office Optimization  
 

Salaries and wages

6,650,200 
 

Employee benefits

807,400 
 

Transportation and communication

47,500 
 

Services

99,989,000 
 

Supplies and equipment

58,300 
 

Subtotal

107,552,400 
 

Less: recoveries

29,376,90078,175,500
 Total operating expense to be voted 380,168,800
4006-5Legislative Building Restoration  
 

Salaries and wages

 867,300
 

Employee benefits

 128,000
 

Services

 6,095,800
 Total operating expense to be voted 7,091,100
 Statutory appropriations  
 

Other transactions

  
Statutory

Bad Debt Expense, the Financial Administration Act

 144,000
 Statutory appropriations  
Statutory

Parliamentary Assistant's Salary, the Executive Council Act

 16,173
 Total operating expense for Government Real Estate 387,420,073
 Capital expense  
4006-2Government Real Estate  
 

Services

 252,502,800
 

Transfer payments

  
 

Realty Transactions - Capital

 1,000
 

Other transactions

 15,800,800
 Total capital expense to be voted 268,304,600
4006-3Government Real Estate – Capital expense Related to Capital assets  
 

Other transactions

 1,000
 Total capital expense to be voted 1,000
 Statutory appropriations  
 

Other transactions

  
Statutory

Amortization, the Financial Administration Act

 1,289,400
 Total capital expense for Government Real Estate 269,595,000
 Capital assets  
4006-4Government Real Estate  
 

Land

 11,230,000
 

Buildings - asset costs

 9,277,600
 

Buildings – alternative financing and procurement

 133,667,800
 

Machinery and equipment - asset costs

 21,366,300
 Total capital assets to be voted 175,541,700
 Total capital assets for Government Real Estate 175,541,700

Infrastructure Partnership Projects & Agency Oversight - Vote 4007

The Government Infrastructure Projects & Agency Oversight Program oversees the Transit-Oriented Communities (TOC) Program in partnership with Infrastructure Ontario and Metrolinx. The TOC Program is part of the government’s plan to build vibrant, sustainable, mixed-use communities near transit, while reducing the burden on taxpayers to build transit station infrastructure. TOCs are anticipated to increase ridership, reduce congestion and provide a mix of housing, including affordable housing options, while creating jobs.

The program is also working with Infrastructure Ontario on the redevelopment of Ontario Place as a world-class, year round destination that will include family-friendly entertainment, public and event spaces, parkland, and waterfront access.

As part of its agency oversight role, the program works closely with Infrastructure Ontario and the Toronto Waterfront Revitalization Corporation to ensure that their mandates are aligned with the province’s priorities. The program works with partners and sponsor ministries to develop and issue direction to Infrastructure Ontario in a timely, clear, and effective manner. It also monitors the Infrastructure Ontario lending program and policy framework, and works with Infrastructure Ontario to develop policies and initiatives to enhance infrastructure delivery.

The ministry is also working to move the Ontario Science Centre to Ontario Place, creating a new state-of-the-art facility.

Vote summary

Item numberItem

Estimates
2024-25 $

Estimates
2023-24 $

Difference
between
2024-25
and
2023-24 $

Actual
2022-23 $

Operating expense

1Infrastructure Partnership Projects & Agency Oversight49,107,70032,266,00016,841,70029,734,780
 Total operating expense to be voted49,107,70032,266,00016,841,70029,734,780
 Total operating expense49,107,70032,266,00016,841,70029,734,780

Operating assets

-Infrastructure Partnership Projects-171,230,800(171,230,800)-
 Total operating assets to be voted-171,230,800(171,230,800)-
 Total operating assets-171,230,800(171,230,800)-

Capital expense

2Infrastructure Partnership Projects484,401,800373,535,300110,866,50020,227,200
 Total capital expense to be voted484,401,800373,535,300110,866,50020,227,200
SAmortization, the Financial Administration Act200,000-200,000-
 Total statutory appropriations200,000-200,000-
 Total capital expense484,601,800373,535,300111,066,50020,227,200

Capital assets

3Infrastructure Partnership Projects88,086,30055,924,00032,162,300-
 Total capital assets to be voted88,086,30055,924,00032,162,300-
 Total capital assets88,086,30055,924,00032,162,300-

Standard account by item and sub-items

Vote-
item
number
Standard account by item and sub-itemsAmount $Amount $Amount $

Operating expense

4007-1Infrastructure Partnership Projects & Agency Oversight   
 

Salaries and wages

  10,244,400
 

Employee benefits

  1,165,600
 

Transportation and communication

  289,000
 

Services

  17,549,100
 

Supplies and equipment

  188,100
 

Transfer payments

   
 

Ontario Science Centre

 19,271,500 
 

Ontario Place Redevelopment Operating expense

 400,00019,671,500
 Total operating expense to be voted  49,107,700
 Sub-items:   
 Transit–Oriented Communities & Agency Oversight   
 

Salaries and wages

 4,374,500 
 

Employee benefits

 448,800 
 

Transportation and communication

 154,500 
 

Services

 12,099,300 
 

Supplies and equipment

 37,40017,114,500
 Ontario Place Redevelopment Secretariat   
 

Salaries and wages

 5,869,900 
 

Employee benefits

 716,800 
 

Transportation and communication

 134,500 
 

Services

 5,449,800 
 

Supplies and equipment

 150,700 
 

Transfer payments

   
 

Ontario Science Centre

19,271,500  
 

Ontario Place Redevelopment Operating expense

400,00019,671,50031,993,200
 Total operating expense to be voted  49,107,700
 Total operating expense for Infrastructure Partnership Projects & Agency Oversight  49,107,700
 Capital expense   
4007-2Infrastructure Partnership Projects   
 

Services

  120,951,800
 

Transfer payments

   
 

East Harbour Transit-Oriented Communities

 333,250,000 
 

Toronto Waterfront Revitalization

 30,200,000363,450,000
 Total capital expense to be voted  484,401,800
 Statutory appropriations   
 

Other transactions

   
Statutory

Amortization, the Financial Administration Act

  200,000
 Total capital expense for Infrastructure Partnership Projects & Agency Oversight  484,601,800
 Capital assets   
4007-3Infrastructure Partnership Projects   
 

Dams and engineering structures - asset costs

  88,086,300
 Total capital assets to be voted  88,086,300
 Total capital assets for Infrastructure Partnership Projects & Agency Oversight  88,086,300